To secure power flow from the Southern part of the country, the CEB isconstructing a second 66kV line on concrete pole from Champagne to Wooton over a route of some 20 km. This network line was commissioned in 2017.
To ensure the N-1 security criteria to the Anahita substation, a second FUEL-Anahita 66kV was constructed. The project was implemented in 2018.